MCQs 1: The time corresponding to minimum total project cost is_______________?

MCQs 2: During the construction period, price variation clause in contracts caters to__________________?

MCQs 3: Sinking fund is_______________?

MCQs 4: In resources levelling________________?

MCQs 5: PERT is preferred for planning because of________________?
Consider the following features/factors
1. Projects are of the non-repetitive type.
2. Time required need not be known.
3. Time required is known precisely.
4. Events have been established for planning.
5. Emphasis is given to activities of project

MCQs 6: The correct sequence of these operations in tunnel construction is______________?
Consider the following operations :
1. Drilling
2. Blasting
3. Mucking
4. Placing steel
5. Placing concrete

MCQs 7: The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is________________?

MCQs 8: Which one of the following is not an excavating and moving type of equipment ?

MCQs 9: For excavating utility trenches with precise control of depth, the excavation equipment used is_______________?

MCQs 10: Batching refers to________________?