MCQs 1: The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted, and pneumatic tyremounted machines would be respectively_________________?

MCQs 2: In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having________________?

MCQs 3: Wheeled tractors are replacing crawler tractors because________________?
Consider the following statements?
1. wheeled tractors travel faster
2. crawler tractors are more expensive
3. track parts of a crawler wear out quickly
4. crawler tractors have stick control

MCQs 4: Sensitivity analysis is a study of__________________?

MCQs 5: Preliminary project report for a road project must contain___________________?

MCQs 6: The basic action involved in sheep foot rolling is_______________?

MCQs 7: The most suitable type of equipment for compaction of cohesive soils is_________________?

MCQs 8: Grader is used mainly for___________________?

MCQs 9: For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is__________________?

MCQs 10: The correct sequence of these activities is________________?
Consider the following activities in a building construction?
1. Concreting of roof slabs
2. Brick-jelly lime concrete terracing
3. Erection of form work for slab
4. Construction of parapet wall in terrace